Lianyan Railway
Lianyungang to Yancheng railway bridge erection project
Lianyan Railway Section II is the Lianzhen Railway introduction reverse departure line operation line (adjacent) laying and erection project. It corresponds to both the existing Longhai Line and the existing Qingyan Line, including over existing line beam erection and beam erection at both ends of the existing line.
Although projects adjacent to and crossing existing lines have long been not the first attempt for Jianghe Heavy Industry, it is still a project with high safety requirements. Especially since the Longhai Line is a busy main line, all processes must be carried out in an orderly manner according to the construction plan and schedule.
On the night of July 17, 2020, Mr. Song of Jianghe Heavy Industry led the team to the site and supervised the cross-line erection together with the leaders of China Railway 11th Bureau. From then on, Jianghe Heavy Industry's team began nearly 20 days of continuous night work until August 5, when the cross-line project was completed.
After completion, the main line of Lianyan Railway is Class I national railway, and the branch line is Class II national railway, becoming the fast railway channel from Qingdao to Shanghai.